What's happened on site this period?

02 Jan 18 to 02 Mar 18:       

  • Ongoing facing brickwork and stonework to numerous buildings

  • Facing brickwork and stone to all buildings nearing completion

  • Scaffold strip following brickwork and stonework completion to external walls

  • Completion of remaining timber sash windows & French doors

  • Internal plasterboard partition installations substantially complete

  • Plasterboard and suspended ceilings substantially complete

  • Commissioning of MEP installations commencing to all buildings, with final fix progressing in all areas

  • Continuation of building services commissioning, with permanent power, light and heat on

  • Final joinery installations, vinyl flooring and decoration to all buildings

  • Final furniture, fittings and equipment installation ongoing

  • Progressive continuation of snagging as buildings complete

  • Building completion inspections ongoing

  • Continuation of external masonry refurbishment to Stanford Hall

  • Continuation of internal fit out and decoration within Stanford Hall

  • Scaffold strip to Stanford Hall following envelope refurbishment

  • Hard and soft landscaping works progressing to all external areas and courtyards

  • External landscaping, lighting, fencing and internal roads nearing completion

  • External sports facilities: Sports pitch, Outdoor equipment bases & north boundary footpath nearing completion

  • Works to heritage features, the Game House, HaHa refurbishment, Tennis & Garden Pavilions, Eastern boundary wall, Sea Lion pool works nearing completion

  • Commencement of the new Garden Pavilion foundations and structural frame

  • Specialist fit out commences

  • Ongoing installation of external new retaining walls & refurbishment of existing walls

  • External walls and roofing works completed for new Estate Yard

  • Prosthetics fit out commenced