Activity on site in the coming weeks

05 Mar 18 to 13 May 18:    

  • Removal of the last two tower cranes

  • Completion of final roof flashings and downpipes

  • Facing brickwork and stone substantially completed, with final snagging and sign off ongoing

  • Removal of remaining external scaffolds

  • Continuation of building services final installations and commissioning, with progressive permanent power, light and heat on

  • Final joinery installations, vinyl flooring and decoration to remaining buildings

  • Final furniture, fittings and equipment installation ongoing

  • Progressive continuation of snagging and sign off as rooms are completed

  • Handover of buildings as they are completed

  • External masonry refurbishment to Stanford Hall substantially complete and scaffold removed

  • Continuation of internal fit out and decoration within Stanford Hall

  • Hard and soft landscaping works to external areas and courtyards with lighting, fencing and planting nearing completion, with progressive snagging and sign off as areas are completed

  • Heritage works nearing completion; with the Game House, Ha Ha refurbishment, Tennis and Garden Pavilions, wall, Sea Lion pool etc

    Garden Pavilion ground floor slab placed, with roof, cladding, brickwork and windows to commence

  • Specialist fit out works ongoing

  • Prosthetics fit out on going

  • Estate Yard practical completion