What's happened on site this period?

17 Feb 17 to 07 Apr 17:      

  • Ongoing structural steel building frames, including roof steel frames
  • Ongoing SFS installation to the Prosthetics building
  • Ongoing intumescent treatment to steel structural frames
  • Ongoing roofing installation to the Integrated Treatment Area and SNCOs Accommodation building
  • Ongoing facing brickwork to numerous buildings
  • Ongoing installation of windows & French doors to the Ward Block, Integrated Treatment Area & Force Generation Accommodation
  • Ongoing delivery and installation of the Ward block bedroom  and SNCO’s Accommodation en-suite toilet pods
  • Ongoing MEP installations to the Ward block, Neuro Therapy, Integrated Treatment Area and SNCO's Accommodation
  • Internal plasterboard partition installation ongoing to the Ward block, Neuro Therapy, Integrated Treatment Area and SNCO's Accommodation
  • Internal blockwork wall installation ongoing in the Pool Complex area
  • Ongoing substructure ground works to Stanford Hall new ‘wrap’ building nearing completion
  • Substructures to the Stores building are now complete with the steel work starting shortly
  • Ongoing existing window and external masonry refurbishment to Stanford Hall
  • External façade works to the Bothy and Gardener Cottage ongoing
  • East Car park works on going
  • External sports facilities: Hand cycle route works have commenced
  • Building service entry points have started and are well underway
  • Works to heritage features, the HaHa refurbishment and the eastern boundary wall have commenced
  • Start of essential works along the southern boundary of the Stanford Hall Estate