What's happened on site this period?

29 Sep 17 to 22 Dec 17:       

  • Ongoing facing brickwork and stonework to numerous buildings

  • Ongoing external wall scaffold strip has commenced to facilitate the hard landscaping works

  • Ongoing installation of windows & French doors to the final buildings 

  • Ongoing MEP installations including lifts to the Ward block, Neuro Therapy, Integrated Treatment Area and Staff Accommodation

  • Incoming services are ‘live’ with HV power, gas and water

  • Continuation of internal plasterboard partition installations in the final buildings

  • Continuation of plasterboard ceilings in the Integrated Treatment Area and Accommodation areas

  • Continuation of vinyl flooring and decoration in the Ward block & Integrated Treatment Area

  • Final joinery installations ongoing in the Ward block, including doors and FF&E

  • Ongoing existing window, external masonry and roof refurbishment to Stanford Hall

  • Continuation of internal fit-out within Stanford Hall

  • External façade works to the Bothy and Gardeners Cottage complete

  • East Car park and Service Yard external works on going

  • External courtyards ongoing

  • External lighting and fencing ongoing

  • External sports facilities: Sports pitch, Outdoor equipment bases & north boundary footpath ongoing

  • Continuation of works to heritage features, Ha Ha refurbishment, Tennis Pavilion complete , Garden  Pavilions ongoing, Eastern boundary  wall complete, Sea Lion pool works continue

  • Ongoing installation of external retaining walls

  • Essential works along the southern boundary of the Stanford Hall Estate including dam repairs and revetment works to the Duke’s lake completed

  • Pitch and putt course and the laying of tees and greens complete

  • Excavation and ground works commenced for new Estate Yard