What's happened on site this period?

21 Jul 17 to 29 Sep 17:        

  • Ongoing roofing installation to the final buildings
  • Ongoing facing brickwork and stone to numerous buildings
  • Ongoing external wall scaffold strip has commenced to facilitate the hard landscaping works
  • Ongoing installation of windows & French doors to the final buildings
  • Ongoing MEP installations including lifts to the Ward block, Neuro Therapy, Integrated Treatment Area and Staff Accommodation
  • Internal plasterboard partition installations ongoing in the final buildings
  • Installation of plasterboard ceilings ongoing in the Integrated Treatment Area and Accommodation areas
  • Vinyl flooring and decoration ongoing in the Ward block & Integrated Treatment Area
  • Final joinery installations ongoing in the Ward block, including doors and FF&E
  • Ongoing existing window, external masonry and roof refurbishment to Stanford Hall
  • Internal fit out ongoing within Stanford Hall
  • External façade works to the Bothy and Gardeners Cottage nearing completion
  • East Car park and Service Yard external works on going
  • External courtyards ongoing
  • External lighting and fencing ongoing
  • External sports facilities: Sports pitch, Outdoor equipment bases & north boundary footpath ongoing
  • Works to heritage features, the HaHa refurbishment, Tennis & Garden Pavilions, Eastern boundary wall, Sealion Pool works are ongoing
  • Ongoing installation of external retaining walls
  • Continuation of essential works along the southern boundary of the Stanford Hall Estate including dam repairs and revetment works to the Duke’s lake
  • Completion of the pitch and putt course and the laying of tees and greens