Activity on site in the coming weeks

15 May 17 to 16 Jun 17:  

  • Ongoing foundations & drainage to Ancillary buildings
  • Back to Life, Gate House & Patients Mess structural frames nearing completion
  • Ongoing intumescent treatment to steel structural frames
  • Ongoing SFS installation to the Prosthetics building
  • Ongoing roofing installation to the Integrated Treatment Area, SNCO’s & Force Generation Accommodation and Prosthetics buildings
  • Ongoing facing brickwork and stone to numerous buildings
  • Ongoing installation of windows & French doors to the Ward block, Integrated Treatment Area, Force Generation & SNCO’s Accommodation
  • Ongoing delivery and installation of the Force Generation and Staff Accommodation en-suite toilet pods
  • Ongoing MEP installations including lifts to the Ward block, Neuro Therapy, Integrated Treatment Area and Staff Accommodation
  • Internal plasterboard partition installations ongoing to the Ward block, Neuro Therapy, Integrated Treatment Area and Staff Accommodation
  • Internal blockwork wall installation ongoing in the Pool Complex area
  • Installation of plasterboard ceilings ongoing in the Ward block & Integrated Treatment Area
  • Vinyl flooring and decoration commencing in the Ward block
  • Ongoing structural steel frame and metal decking to Stanford Hall new ‘wrap’ building
  • Ongoing existing window, external masonry and roof refurbishment to Stanford Hall
  • Internal fit out ongoing within Stanford Hall
  • External façade works to the Bothy and Gardeners Cottage nearing completion
  • East Car park works on going
  • The phase of the site internal road installation ongoing
  • External sports facilities: Outdoor equipment bases & north boundary footpath ongoing
  • Building service entry points progressing
  • Works to heritage features, the HaHa refurbishment, Tennis & Garden Pavilions, Eastern boundary wall, Sealion Pool works are ongoing
  • Ongoing installation of external retaining walls