Activity on site in the coming weeks

02 Oct 17 to 04 Nov 17:  

  • Ongoing roofing installation and flashings to the final buildings
  • Facing brickwork and stone continuing to numerous buildings
  • Ongoing external wall scaffold strip following brickwork and stone completion
  • Hard landscaping works progressing to external areas and courtyards
  • Ongoing final installation of windows & french doors
  • Internal plasterboard partition installations now substantially complete
  • Installation of plasterboard and suspended ceilings ongoing
  • Ongoing MEP installations to all buildings, with final fix progressing in the Ward block, Integrated Treatment Area and Accommodation areas
  • Incoming services are ‘live’ with HV power, with gas and water
  • Building services commissioning has commenced and permanent lighting has been energised in the Ward block
  • Final joinery installations, Vinyl flooring and decoration ongoing in the Ward block, Integrated Treatment Area and Accommodation areas

    Building completion snagging has commenced
  • Ongoing existing window, external masonry and roof refurbishment to Stanford Hall
  • Internal fit out and decoration ongoing within Stanford Hall
  • Scaffold strip ongoing to Stanford Hall following envelope refurbishment
  • External courtyards ongoing
  • External landscaping, lighting, fencing and internal roads ongoing
  • External sports facilities: Sports pitch, Outdoor equipment bases & north boundary footpath ongoing
  • Works to heritage features, the Game House, HaHa refurbishment, Tennis & Garden Pavilions, Eastern boundary wall, Sealion Pool works are ongoing
  • Ongoing installation of external new retaining walls & refurbishment of existing walls
  • Completion of essential works along the southern boundary of the Stanford Hall Estate including dam repairs and revetment works to the Duke’s lake