Activity on site in the coming weeks

02 Jan 18 to 02 Mar 18:  

  • Completion of final roof flashings and downpipes to all buildings

  • Facing brickwork and stone to numerous buildings substantially competed

  • Scaffold strip following brickwork and stonework completion to external walls

  • Hard landscaping works progressing to external areas and courtyards

  • Ongoing installation of remaining windows & French doors

  • Internal plasterboard partition installations substantially complete

  • Completion of plasterboard and suspended ceilings

  • Commissioning of MEP installations commencing to all buildings, with final fix progressing in all areas

  • Continuation of building services commissioning, with permanent power, light and heat on

  • Final joinery installations, vinyl flooring and decoration to all buildings

  • Final furniture, fittings and equipment installation ongoing

  • Progressive continuation of snagging as buildings complete

  • Building completion inspections ongoing

  • Continuation of external masonry refurbishment to Stanford Hall

  • Continuation of internal fit out and decoration within Stanford Hall

  • Scaffold strip to Stanford Hall following envelope refurbishment

  • External courtyards ongoing

  • External landscaping, lighting, fencing and internal roads nearing completion

  • External sports facilities: Sports pitch, Outdoor equipment bases & north boundary footpath nearing completion

  • Works to heritage features, the Game House, HaHa refurbishment, Tennis & Garden Pavilions, Eastern boundary wall, Sea Lion pool works nearing completion 

  • New Estate yard steel frame erection started, external walls and roofing to commence